AGENDA TITLE:
title
Approve Plans and Specifications and Authorize Advertisement for Bids for the Surface Water Treatment Facility Generator Upgrade Project (PW)
end
MEETING DATE:
August 7, 2024
PREPARED BY:
Public Works Director
recommendation
RECOMMENDED ACTION:
Approve plans and specifications and authorize advertisement for bids for the Surface Water Treatment Facility Generator Upgrade Project.
body
BACKGROUND INFORMATION:
The Surface Water Treatment Facility ("SWTF") provides approximately fifty percent (50%) of Lodi's annual drinking water supply. Twenty-eight (28) municipal groundwater wells throughout the City provide the remaining 50% of the supply, eight of which are fitted with diesel-powered generators.
When commissioned in 2012, the SWTF included a back-up generator that would provide minimal power to operate the SCADA system and other ancillary functions of the facility. At that time, it was decided not to include a back-up generator sized to process and deliver drinking water to the distribution system. This decision was based on the unlikely event of a long-term power interruption.
While the City's electrical system is safe and reliable, the State's power grid has grown increasingly unreliable due to statewide demand and natural disasters such as wildfires. The increased frequency of Public Safety Power Shut Offs (PSPS) imposed by PG&E, coupled with additional power demands increases the risk of long-term power outages. Because of the increased concern that long-term outages outside of the City's control will become more frequent, there is an increased need for an upgraded generator that will provide 100% back-up power at the SWTF.
This project includes the installation and system integration of a new 800KW generator for the SWTF (Exhibit A) to allow the plant to be fully operational during power outages. On February 19, 2003, the City Council approved Olympian (supplied by Caterpillar) as the standard for standby el...