Legislation Details

File #: 24-394    Name: Garney CO No 1
Type: Resolution Status: Agenda Ready
File created: 9/9/2024 In control: City Council
On agenda: 10/2/2024 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution Authorizing the City Manager to Execute Change Orders for the Solids Handling Facility Improvements at White Slough Water Pollution Control Facility in an Amount Not-To-Exceed $150,000 (PW)
Attachments: 1. Attachment 1 - Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Adopt a Resolution Authorizing the City Manager to Execute Change Orders for the Solids Handling Facility Improvements at White Slough Water Pollution Control Facility in an Amount Not-To-Exceed $150,000 (PW)
end

MEETING DATE:
October 2, 2024

PREPARED BY:
Public Works Director


recommendation
RECOMMENDED ACTION:
Adopt a Resolution authorizing the City Manager to Execute Change Orders for the Solids Handling Facility Improvements at the White Slough Water Pollution Control Facility in an amount not-to-exceed $150,000.

body
BACKGROUND INFORMATION:
On April 15, 2020, Council authorized the City Manager to execute a Professional Services Agreement with Carollo Engineers, Inc. to provide professional design services to evaluate the need for sludge dewatering press and digester mixing system upgrades at the White Slough Water Pollution Control Facility (WSWPCF). This contract was procured in accordance with Lodi Municipal Code Section 3.20.075.

In certain conditions, the performance of the existing sludge dewatering equipment at WSWPCF cannot remove the amount of moisture needed to properly handle the material. Carollo Engineers recommended that a new screw press and sludge mixing system was needed to improve the sludge dewatering process.

On January 18, 2023, and in accordance with the California Contract Code, Council awarded a contract for Solids Handling Facility Improvements at the WSWPCF, to Garney Pacific Inc, in the amount of $2,424,725. The approval did not authorize City Manager change order authority. Standard practice for the City when approving Public Works contracts is to include an allowance for change orders due to unforeseen changes in scope, materials pricing or quantity to complete the project. This project required work beyond the original scope.

Currently, there is 1 change order that included approximately $5,000 of work necessary to repair an 18" pipeline within the headworks area that serves the ind...

Click here for full text