Legislation Details

File #: 24-439    Name: Accept Playground Replacement
Type: Report/Consent Status: Agenda Ready
File created: 10/16/2024 In control: City Council
On agenda: 12/4/2024 Final action:
Enactment date: Enactment #:
Title: Accept Improvements Under Contract for the 2023 Playground Replacement Project (PW)
Attachments: 1. Attachment 1 - Exhibit A
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Accept Improvements Under Contract for the 2023 Playground Replacement Project (PW)
end

MEETING DATE:
December 4, 2024

PREPARED BY:
Public Works Director


recommendation
RECOMMENDED ACTION:
Accept Improvements under contract for the 2023 Playground Replacement Project.

body
BACKGROUND INFORMATION:
On October 18, 2023, Council authorized advertisement for bids for the 2023 Playground Replacement Project; authorized the City Manager to award a contract to the lowest responsive bidder in an amount not-to-exceed $1,560,000; and authorized the City Manager to execute change orders in an amount not-to-exceed $105,000.

The project replaced outdated and aging playground structures at five city parks to meet current playground equipment safety requirements. The affected parks, along with their corresponding original installation dates included: English Oaks (1997), Hale Park (2006), Katzakian Park (2001), Legion Park (1997-1998), and Peterson Park (1997).

The new playgrounds and safety surfacing were designed to comply with the Americans with Disabilities Act (ADA), Consumer Product Safety Commission guidelines, and American Society for Testing and Materials (ASTM) Standards. Each park was inspected by a Certified Playground Safety Inspector and received certificates demonstrating compliance with the above-mentioned standards.

In addition to replacing the outdated play equipment, the project also repaired broken concrete flatwork, installed new accessible parking stalls and ramps, new ADA signage, playground safety surfacing, and park benches.

The contract time (after building permit issuance) allowed for a 100-calendar day construction window and construction was completed in 78 days. The project required three change orders totaling $67,023.10, making the total contract price $1,365,772.10. Change order work included removing and replacing additional concrete at each of the parks, installing new accessible parking stalls...

Click here for full text