Title: Accept Improvements Under Contract for Lincoln Avenue Storm Pump Station Rehabilitation (PW)
Attachments: 1. Attachment 1 - Exhibit A - SiteMap, 2. Attachment 2 - Exhibit B
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Accept Improvements Under Contract for Lincoln Avenue Storm Pump Station Rehabilitation (PW)
end

MEETING DATE:
December 18, 2024

PREPARED BY:
Public Works Director


recommendation
RECOMMENDED ACTION:
Accept Improvements for Lincoln Avenue Storm Pump Station Rehabilitation.

body
BACKGROUND INFORMATION:
Built in 1969, the Lincoln Avenue Pump Station was designed to lift storm water captured within the Outfall 9 Boundary (Exhibit A), and discharge into the Mokelumne River when the river is running too high to discharge by gravity. The single pump and control panel were beyond the useful life and needed replacement to comply with current industry standards.

This project consisted of rehabilitating the storm drain pump station including the replacement of the pump, pump motor, and pump control panel; rehabilitation of the force main and wet well; all necessary wiring of pump station system components; and other incidental and related work, all as shown on the specifications for the above project. The new pump motor control panel regulates voltage, provides better pump efficiency, and complies with current electrical standards.

Council approved plans, specifications, advertisement, and the award authority on September 6, 2023. Bids were received on November 1, 2023, with Clyde G. Steagall, Inc. being the lowest bidder (see breakdown below). All work was completed in substantial conformance with the plans and specifications approved by City Council. The final contract price was $248,803.71, including one change order in the amount of $5,392.71.

Change Order No. 1 included extra work required to fabricate and install two steel braces connected to the pump support beam to reduce pump vibration.

Bidder
Location
Bid
Above/(Below) Engineer's Estimate
Engineer's Estimate
$300,000.00
Clyde G. Steagall, Inc.
Loomis
$243,411.00
($56,589.00)
Howk Systems, Inc.
Modesto
$287,000.00
($13,000.00)
ARB, Inc.
Pittsburg
$294,8...