AGENDA TITLE:
title
Accept Improvements Under Contract for Hutchins Street Resurfacing Project (PW)
end
MEETING DATE:
November 5, 2025
PREPARED BY:
Public Works Director
recommendation
RECOMMENDED ACTION:
Accept improvements under contract for Hutchins Street Resurfacing Project.
body
BACKGROUND INFORMATION:
On May 7, 2025, Council awarded the Hutchins Street Resurfacing project to Knife River Construction in the amount of $1,370,475 and authorized the City Manager to execute change orders in an amount not-to-exceed $150,000. This project included localized pavement repair, the application of approximately 31,000 square yards of rubberized asphalt chip seal and fiberized slurry seal. The project limits were Hutchins Street, from Lodi Ave to Kettleman Lane. Before and after photos are shown on Exhibit A.
The rubberized asphalt cape seal is a combination of a rubberized chip seal comprising the bottom layer followed with an upper layer of fiberized slurry seal (slurry seal with strands of glass fiber added). In addition, there were 36 curb ramps reconstructed to current ADA standards.
All work was completed in substantial conformance with the plans and specifications approved by City Council. The final contract price was $1,440,290.08 with two change orders that totaled $69,815.08.
Change Order No. 1 ($34,483.93) included additional work to modify existing pedestrian push buttons to make the curb ramps at the signal poles ADA compliant.
Change Order No. 2 ($35,331.15) included minor additional quantities for chip and slurry seal, traffic loops, and traffic box lids as requested by the City.
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is complete and begins their 30-day period to file a stop notice requiring the City to withhold payments from the prime contr...