AGENDA TITLE:
title
Adopt a Resolution Authorizing an Increase of the City Manager’s Change Order Authority From $100,000 to a Total Amount Not-to-Exceed $235,000 for the Central Plume PCE/TCE Soil Vapor Remediation Project (PW)
end
MEETING DATE:
October 21, 2026
PREPARED BY:
Sean Nathan, Deputy Public Works Director
/
recommendation
RECOMMENDED ACTION:
Adopt a Resolution authorizing an increase of the City Manager’s change order authority from $100,000 to a total amount not-to-exceed $235,000 for the Central Plume PCE/TCE Soil Vapor Remediation Project.
body
BACKGROUND INFORMATION:
For over 20 years the City of Lodi has been involved in the remediation efforts associated with perchloroethylene (PCE) in the Central Plume Source Area (CPSA). The CPSA is generally bound by Pine Street on the North, Oak Street on the South, Church Street on the East, and Pleasant Street on the West. While the City did not cause the soil and groundwater contamination, the City agreed to assume all of the cleanup obligations as part of multiple lawsuit settlements.
On July 2, 2025, Council approved the plans and specifications for the Central Plume PCE/TCE Soil Vapor Remediation Project, authorized the advertisement for bids, authorized the award to the lowest responsive bidder ($1,000,000), authorized change orders ($100,000), and appropriated funds ($1,100,000).
On July 1, 2026, Council approved the reimbursement agreement with Pine Street Partners, LLC, in an amount not to exceed $135,000. The agreement was established in conjunction with the $135,000 contract credit from Innovative Construction Solutions (ICS), allowing the contractor to demolish the interior walls without reconstructing them and providing the property owner flexibility to reconfigure the interior as part of its future remodel.
On July 14, 2026, Innovative Construction Solutions (ICS) began work to remove the interior walls and demolish the existing concrete floor in accordance with the ap...