AGENDA TITLE:
title
Adopt a Resolution Authorizing City Manager to Award Contract For Guild Avenue and Victor Road (SR 12) Traffic Signal and Lighting Project to St. Francis Electric, LLC. of San Leandro ($903,999) and Authorizing City Manager to Execute Change Orders ($100,000), and Appropriate Funds ($100,000) (PW)
end
MEETING DATE:
November 6, 2024
PREPARED BY:
Public Works Director
recommendation
RECOMMENDED ACTION:
Adopt a Resolution authorizing City Manager to award contract for Guild Avenue and Victor Road (SR 12) Traffic Signal and Lighting Project to St. Francis Electric, LLC. of San Leandro in the amount of $903,999, authorizing the City Manager to execute Change Orders in an amount not-to-exceed $100,000, and appropriate funds in the amount of $100,000.
body
BACKGROUND INFORMATION:
Steady growth in the industrial area east of SR 99 has resulted in additional traffic impacts at the intersection at Victor Road (SR 12) and Guild Avenue. After receiving several requests for a traffic signal installation at this location staff conducted a traffic signal evaluation that determined this intersection met the State criteria. Currently, this intersection is a 4-way intersection with stop controls on Guild Avenue.
Victor Road (SR 12) is a Caltrans owned roadway. All improvements proposed within the Caltrans right-of-way require an approved encroachment permit issued by Caltrans before construction is authorized. The Caltrans encroachment permit was issued to the City in May 2024.
This project installs curb ramp, crosswalk, traffic signal and lighting improvements at the Guild Avenue and Victor Road (SR 12) intersection. This project will also relocate the raised median on Guild Avenue north of Victor Road to accommodate large truck turning movements as required by Caltrans.
On August 7, 2024, Council approved the plans and specifications and authorized advertisements for bids. The City received the following eight bids for this project on September 18, 2024:
Bidder |
Location |
Bid |
Above/(Below) Estimate |
Engineer’s Estimate |
$806,120.00 |
*Mike Brown Electric Co. |
Cotati |
$861,690.00 |
$55,570.00 |
St. Francis Electric, LLC |
San Leandro |
$903,999.00 |
$97,879.00 |
Tim Paxon’s Pacific Excavation, Inc |
Elk Grove |
$949,957.00 |
$143,837.00 |
Tennyson Electric LLC |
Livermore |
$987,124.50 |
$181,004.50 |
PTM General Engineering Services Inc |
Riverside |
$989,089.00 |
$182,969.00 |
B&M Builder, Inc. |
Rancho Cordova |
$1,036,970.00 |
$230,850.00 |
Columbia Electric, Inc |
San Leandro |
$1,097,096.50 |
$290,976.50 |
**Zara Construction Inc |
Sacramento |
$1,136,285.00 |
$330,165.00 |
*Bid deemed nonresponsive due to incorrect subcontractor license number per Public Contract Code Section 4104(a)(2)
**Bid deemed nonresponsive due to failure to submit receipt of Addendum 1
Staff recommends adopting a resolution authorizing the City Manager to award contract for Guild Avenue and Victor Road (SR 12) Traffic Signal and Lighting Project to St. Francis Electric, LLC. of San Leandro in the amount of $903,999, and authorizing the City Manager to execute change orders in an amount not-to-exceed $100,000, and appropriate funds in the amount of $100,000.
STRATEGIC VISION:
5. Infrastructure: Develop and maintain a robust infrastructure to support a World class city.
FISCAL IMPACT:
Installation of this large signal project is anticipated to improve the flow of truck traffic while enhancing safety at this intersection. This project does not impact the General Fund and will have a minimal impact on citywide traffic signal maintenance costs.
FUNDING AVAILABLE:
Street Impact Fees (30899000.77020) PWST - 0043.Contracts $954,850
Requested Appropriation:
Street Impact Fees (30899000.77020) PWST - 0043.Contracts $100,000
_______________________________________
Charles E. Swimley
Public Works Director
_______________________________________
Scott R. Carney
City Manager