AGENDA TITLE:
title
Adopt a Resolution Awarding Contract for Lodi Lake Park North Restroom Restoration Project to Kaler General Contractors, Inc., of Rancho Cordova, California ($469,000) and Authorize City Manager to Execute Change Orders ($100,000); Not to Exceed ($569,000) (PRCS)
end
MEETING DATE:
March 5, 2025
PREPARED BY:
Christina Jaromay, Parks, Recreation and Cultural Services Director

recommendation
RECOMMENDED ACTION:
Adopt a Resolution Awarding Contract for Lodi Lake Park North Restroom Restoration Project to Kaler General Contractors, Inc., of Rancho Cordova, California ($469,000) and Authorize City Manager to Execute Change Orders (up to $100,000).
body
BACKGROUND INFORMATION:
The Lodi Lake North restroom was damaged by an arson fire on June 4, 2023. City Council, at its October 18, 2023 meeting, approved a contract with WMB Architects, Inc. of Stockton, California to perform design services. The services include investigation of the damages, construction documents, permitting, bidding assistance, construction support as well as associated American Disabilities Act (ADA) improvements. City staff worked with WMB Architects, Inc. to complete the design, permit and bid documents. This project includes architecture, structural engineering, mechanical engineering, electrical engineering and ADA Code requirements. City staff is working with our insurance carrier on a mutually agreeable settlement. Staff will work with the architects and Kaler General Contractors, Inc. to determine value engineering concepts to establish potential savings that do not alter the design intent of the project. The plans and specifications for this project were approved on November 20, 2024 and publicly advertised as required. The City received the following bids for this project on January 30, 2025.
Above/(Below)
Bidder Location Bid Engineer’s Estimate
Engineer’s Estimate $800,000.00
Kaler General Contractors, Inc. Rancho Cordova $469,000.00 ($331,000.00)
345 Builders Galt $473,600.00 ($326,400.00)
Bickford Construction Lodi $584,999.00 ($215,001.00)
Diede Construction Woodbridge $645,000.00 ($155,000.00)
Bobo Construction Elk Grove $654,032.00 ($145,968.00)
TSI Engineering, Inc. North Highlands $975,786.00 $175,786.00
Staff recommends awarding the contract for Lodi Lake North Restroom Restoration Project to Kaler General Contractors, Inc., of Rancho Cordova, California in the amount of $469,000 and authorizing City Manager to execute change orders in an amount not to exceed $100,000 for a total not to exceed contract amount of $569,000.
FISCAL IMPACT:
This project will replace the fire damaged restroom structure and bring the facility to current ADA code compliance. The total cost to complete the project with this contract award, WMB Architects, Inc.’s services and necessary staff time is estimated to be $740,000. Existing appropriations are available in the amount of $800,000.
FUNDING AVAILABLE:
The City has a self-insured retention (SIR) of $250,000 per incident for property damage. This requires the City to fund the first $250,000 of project costs. The SIR was allocated on July 19, 2023, under Resolution 2023-154 as part of the excess reserve one-time funds. An additional $800,000 was appropriated during the 2024-25 fiscal year budget which will be reimbursed with insurance payments. $84,117 has been spent towards project design services, plan duplication and permit fees.
Available Funding: Property Insurance (66125200.7020) PKCP-24002.Misc S&S $569,000
_______________________________________
Christina Jaromay
Parks, Recreation and Cultural Services Director
_______________________________________
Scott R. Carney
City Manager