Legislation Details

File #: 26-325    Name: Whit Slough Power Cable
Type: Resolution Status: Agenda Ready
File created: 6/17/2026 In control: City Council
On agenda: 7/1/2026 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution Waiving Bid Process and Authorizing Purchase of Power Cable from Anixter Inc. of Benicia for White Slough Water Pollution Control Facility Electrical Building Project and Approve Interfund Charge in the Amount of ($324,620.10) (EU)
Attachments: 1. Attachment 1 - Ordinance No. 2018, 2. Attachment 2 - Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

AGENDA TITLE:                                                                                                                                                                                             

title

Adopt a Resolution Waiving Bid Process and Authorizing Purchase of Power Cable from Anixter Inc. of Benicia for White Slough Water Pollution Control Facility Electrical Building Project and Approve Interfund Charge in the Amount of ($324,620.10) (EU)

end

 

MEETING DATE:                     

July 1, 2026

 

PREPARED BY:                     

Melissa Price, Assistant Electric Utility Director

 

recommendation

RECOMMENDED ACTION:

Adopt a resolution waiving bid process and authorizing purchase of power cable from Anixter Inc. of Benicia for White Slough Water Pollution Control Facility Electrical Building Project and approve interfund charge in the amount of $324,620.10.

 

body

BACKGROUND INFORMATION:

On May 20, 2026, by Resolution 2026-104, City Council authorized Lodi Electric Utility (LEU) to “obtain bids and purchase power cable from the lowest responsive bidder in an amount not-to-exceed $400,000.”

 

In an effort to expedite the purchase as requested by the Public Works Department to avoid project delays, LEU staff quickly obtained quotes from five vendors as listed below and submitted a purchasing requisition to the Finance Department for issuance of a Purchase Order.  LEU staff reached out to six vendors total in an effort to ensure a thorough competitive process was completed, ensuring the best value to the City.

 

Vendor Name                     Amount                                          Delivery Time

Anixter Inc.                     $324,620.10                                              3-5 days

Main Electric                     $326,666.03                                              3-5 days

One Source                     $329,848.58                                              3-5 days

MSC                     $385,770.53                                              2 weeks

Willie Electric                     $313,253.85                                           14-16 weeks

Alameda Electric                       No Quote                                                N/A

 

Upon receiving the requisition and all supporting documentation, including five vendor quotes, the Finance Department determined that obtaining multiple quotes did not adhere to the formal bid process as outlined in the City’s Purchasing Policy and Lodi Municipal Code and therefore required council approval to waive the bid process.

 

Among other tasks, a formal bid process requires specifications and plans be subject to review by City Council prior to solicitation of bids, advertisement and notice inviting bids, a public bid opening, and award of contract.

 

This formal bid process can take eight weeks or longer, exposing the City to fluctuating markets, increased demand and potential material price increases associated with electric materials as well as additional extended daily overhead costs associated with the construction project as contractors are unable to complete the project until such time as LEU is able to deliver power to the new building. 

 

In 2023, City Council recognized these continuing challenges for LEU and enacted changes to provide greater purchasing flexibility via Ordinance 2018 (Attachment 1) which authorizes inventory item purchases up to $250,000 by LEU.  However, in this particular instance, the total purchase amount will exceed the $250,000 limit authorized by Ordinance 2018.

 

Therefore, LEU is requesting City Council waive the bid process and authorize the purchase of power cable from Anixter Inc. of Benicia for $324,620.10 in accordance with Lodi Municipal Code, Section 3.20.070(5) which states “bidding shall be dispensed when the City Council determines that the purchase or method of purchase would be in the best interests of the City.” Procurement delay from the original City Council authorization in May has already resulted in a nearly $17,000 price increase for the materials.  Current pricing from the vendor will be held until July 10, 2026.  Any delay will likely result in a price increase based on current market volatility.

 

FISCAL IMPACT:

Total cost for purchase of power cable, including tax and freight is $324,620.10.

 

FUNDING AVAILABLE:

The power cable will be purchased through the LEU Enterprise Inventory Account (500.13496). An interfund charge will then be completed to allocate the cost to the White Slough Water Pollution Control Facility Electrical Building Improvements Project (53199000.77020 - PWWA-0010.Contracts), ensuring that all project-related expenses are accurately accounted for within the Capital Improvement Project.