AGENDA TITLE:
title
Adopt a Resolution Appropriating Funds for Salas Park Sports Lighting Improvements (Phase 2) from Playground Replacement Project in the Amount of $21,920 and Parks Tree Trimming Project in the Amount of $10,500 for a Total Amount of $32,420 ($32,420) (PRCS)
end
MEETING DATE:
August 20, 2025
PREPARED BY:
Parks, Recreation and Cultural Services Director

recommendation
RECOMMENDED ACTION:
Adopt a resolution appropriating funds for Salas Park Sports Lighting Improvements (Phase 2) from Playground Replacement Project in the amount of $21,920 and Parks Tree Trimming Project in the amount of $10,500 for a total amount of $32,420.
body
BACKGROUND INFORMATION:
Salas Park is Lodi’s primary sports facility for youth baseball, softball, soccer and football. Phase 1 was accepted by City Council on March 16, 2016. Phase 2 will complete the installation of the Musco Sports Lighting system for youth night games and practices at this facility. Phase 2 improvements will include relocation of two of the eight steel poles set in 2016 for better illumination, installation of thirteen (13) new 70' high galvanized steel poles with LED light fixtures, all wiring and integration with the existing Musco Control-Link® Control & Monitoring System and existing switchboard panel, and other incidental and related work, as shown on the plans and specifications for the above project.
On January 15, 2025, Council approved plans and specifications and authorized the City Manager or designee to award the contract to lowest responsive bidder in an amount not-to-exceed $290,000; pre-purchase the sports lighting components from Musco Corporation of Oskaloosa, Iowa for an amount not-to-exceed $960,000; authorize City Manager or designee to execute change orders in an amount not-to-exceed $107,000; and appropriate funds in the amount of $257,628. The bid opening was held April 2, 2025. The City received the following eight bids:
Above/(Below)
Bidder Location Base Bid Engineer’s Estimate
Engineer’s Estimate $290,000
SCC Electric, Inc. Novato $297,500.00 $7,500.00
Collins Electric Company Inc. Stockton $371,668.00 $81,668.00
SacTown Contractors Corp. Sacramento $382,533.00 $92,533.00
dba Sactown Construction Pros
Bockmon & Woody Electric Co., Inc. Stockton $417,000.00 $127,000.00
*California Building Structures, Inc. Modesto $430,000.00 $140,000.00
Tennyson Electric L.L.C. Livermore $615,000.00 $325,000.00
Bear Electrical Solutions L.L.C. Alviso $617,500.00 $327,500.00
St. Francis Electric L.L.C. San Leandro $648,700.00 $358,700.00
*Non-responsive Bid - Did not include Addendum 2
The lowest bid by SCC Electric, Inc. exceeded the amount authorized to award by the City Manager by $7,500. To account for the additional $7,500 and provide change order authority to account for unforeseen construction related costs, staff recommended to Council and Council adopted a resolution on May 21, 2025 awarding contract for Salas Park Sports Lighting Improvements (Phase 2) to SCC Electric, Inc. of Novato, California in the amount of $297,500, authorized City Manager or designee to execute change orders in the amount of $132,500; and appropriated funds in the amount of $32,420. However, the amount of $32,420 requested from Playground Replacement Project Savings (PKCP-24006) was short $10,500. Staff requests $21,920 from Playground Replacement Project Savings (PKCP-24006) and $10,500 from Parks Tree Trimming (PKCP-20002) and re-appropriating to Parks Capital (PKCP-24003).
STRATEGIC VISION:
6C. Parks: Develop & maintain sports/recreational facilities for City & public use including an indoor sports facility.
FISCAL IMPACT:
The new sports lighting system will decrease maintenance and operations costs in the park’s sports lighting system.
FUNDING AVAILABLE:
Staff requests to transfer $21,920 from Playground Replacement Project (PKCP-24006) and $10,500 from Parks Tree Trimming (PKCP-20002) and re-appropriating to Parks Capital (PKCP-24003).
Fiscal Year 2023-24 and 2024-25 Budget
Parks & Rec Capital (PKCP-24003) $500,000
Fiscal Year 2024-25
Parks & Rec Capital (PKCP-24003) $600,000
Previously requested appropriation
From Playground Replacement (PKCP-24006) $257,628
Requested appropriation
From Playground Replacement (PKCP-24006) $21,920
Request appropriation
From Parks Tree Trimming (PKCP-20002) $10,500
TOTAL: $1,390,048