File #: 26-014    Name: Kaler, Lodi Lake North Restroom
Type: Report/Consent Status: Agenda Ready
File created: 12/15/2025 In control: City Council
On agenda: 2/4/2026 Final action:
Enactment date: Enactment #:
Title: Accept Improvements Under Contract for Lodi Lake North Restroom Restoration Project (PRCS)
Attachments: 1. Attachment 1 - Change Orders 1-3, 2. Attachment 2 - Before/After Photos
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Accept Improvements Under Contract for Lodi Lake North Restroom Restoration Project (PRCS)
end

MEETING DATE:
January 7, 2026

PREPARED BY:
Parks, Recreation and Cultural Services Director


recommendation
RECOMMENDED ACTION:
Accept improvements under contract for Lodi Lake North Restroom Restoration Project.

body
BACKGROUND INFORMATION:
The Lodi Lake North restroom was damaged by arson fire on June 4, 2023. At its October 18, 2023 meeting, the City Council approved a contract with WMB Architects, Inc. of Stockton, California (WMB) to perform design services. The services included investigation of the damages, construction documents, permitting, bidding assistance, construction support, as well as associated American Disabilities Act (ADA) improvements. City staff worked with WMB to complete the architecture, structural engineering, mechanical engineering, electrical engineering and ADA Code requirements.

City Council approved plans and specifications on November 20, 2024. After publicly bidding the project, staff recommended and Council approved award on March 5, 2025, of the construction contract for the Lodi Lake North Restroom Restoration Project to Kaler General Contractors, Inc., of Rancho Cordova, California in the amount of $469,000. The Council action also authorized the City Manager to execute changes orders not to exceed $100,000.

The original contract completion was 120 calendar days. The contract work was suspended on August 7, 2025 due to material procurement lead time for the pump control panel. Contract work was reinstated on October 21, 2025 and completed on November 8, 2025. The final contract price was $516,717. The difference between the contract amount and the final contract price is due to three (3) change order adjustments totaling $47,717, refer to Attachment 1.

A general description of each Change Order is noted below.
Change Order 1 ($33,574):
* Changed the toilet partitions from powdered coated ...