AGENDA TITLE:
title
Accept Improvements Under Contract for 2024 DeBenedetti Park South Parking Lot Expansion (PW)
end
MEETING DATE:
February 18, 2026
PREPARED BY:
Interim Public Works Director
recommendation
RECOMMENDED ACTION:
Accept Improvements Under Contract for 2024 DeBenedetti Park South Parking Lot Expansion.
body
BACKGROUND INFORMATION:
In 2013, the accessibility and parking improvements for DeBenedetti Park were completed. This project consisted of two Americans with Disabilities Act (ADA)-compliant parking stalls, accessible paths to the bottom of the north and south basins, and completing the sidewalk along Century Boulevard. In 2014, the Public Works Department added a paved parking lot with 29 standard parking stalls with a turnaround area. In 2017, the parking lot was expanded adding 97 additional standard parking stalls and four additional ADA compliant parking stalls. This project addressed the need for additional parking and better parking lot circulation. Furthermore, portions of the one-mile loop trail were previously unlit, posing safety and security concerns.
This project included:
? Expanding the parking area with 171 additional parking stalls, 5 additional ADA-compliant parking stalls, and 10 electric vehicle (EV) charging stalls.
? Lighting for the new and existing parking areas as well as portions of the one-mile loop trail.
? A two-lane drive aisle to connect the south parking lot to Century Blvd.
? Water main and fire hydrant improvements.
On April 3, 2024, Council approved plans and specifications for the project and authorized advertisement for bids.
On December 4, 2024, bids were opened with the lowest bidder being Western Engineering Contractor Inc. from Loomis. Western Engineering's base bid totaled $1,398,249.00, with bid alternates totaling $267,085.00, for a total combined base bid and alternates of $1,756,104.00.
On January 15, 2025, Council adopted Resolution No. 2025-007, to award the contract...