AGENDA TITLE:
title
Accept Improvements Under Contract for 2024 Downtown Concrete Cleaning (PW)
end
MEETING DATE:
November 6, 2024
PREPARED BY:
Public Works Director
recommendation
RECOMMENDED ACTION:
Accept improvements under contract for 2024 Downtown Concrete Cleaning.
body
BACKGROUND INFORMATION:
In 1998, the City's Central City Revitalization Improvement Project installed yellow colored concrete on School Street, from Lodi Avenue to Locust Street. As part of the maintenance, the colored concrete should be cleaned periodically. In 2019, Council requested that we start cleaning it annually.
This project removed debris and pressure washed the yellow concrete bands, and spot cleaned the paver areas along School Street, between Lodi Avenue and Locust Street. The project also included the large concrete star burst feature located in Elm Street between School Street and Sacramento Street. See the before and after pictures on attached Exhibit A. The work was done at night in order to minimize business interruptions.
On February 7, 2024, the Council approved specifications for this project and authorized the City Manager to award contract to the lowest bidder not-to-exceed $30,000, execute change orders not-to-exceed $3,000, and appropriate funds of $3,000. At the bid opening held on May 15, 2024, the City received the following three bids:
Above/(Below)
Bidder Location Bid Engineer's Estimate
Engineer's Estimate $33,000.00
EcoSanitation, LLC Sacramento $19,869.00 ($13,131)
Sure Clean, Inc Cool $24,720.000 ($8,280)
City Wide Property Services, Inc Rancho Cordova $26,960.000 ($6,040)
The contract was executed on July 29, 2024 with EcoSanitation, LLC, of Sacramento, in the amount of $19,869.00. Work commenced on August 25, 2024 and was completed on September 4, 2024 in substantial conformance with the specifications approved by City Council for the final contract price of $19,869.00. The project was comple...