Legislation Details

File #: 26-298    Name:
Type: Resolution Status: Agenda Ready
File created: 6/8/2026 In control: City Council
On agenda: 8/5/2026 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution Awarding Contract for the Carnegie Forum Boiler Replacement to Mesa Energy Systems, Inc., of West Sacramento ($94,363), Authorizing City Manager to Execute Change Orders ($15,000) and Appropriate Funds from Facilities Office Remodel Project in the Amount of $10,000 and Fire Station 4 Stucco Project in the Amount of $36,183 ($46,183) (PW)
Attachments: 1. Attachment 1 - Contract, 2. Attachment 2 - Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Adopt a Resolution Awarding Contract for the Carnegie Forum Boiler Replacement to Mesa Energy Systems, Inc., of West Sacramento ($94,363), Authorizing City Manager to Execute Change Orders ($15,000) and Appropriate Funds from Facilities Office Remodel Project in the Amount of $10,000 and Fire Station 4 Stucco Project in the Amount of $36,183 ($46,183) (PW)
end

MEETING DATE:
August 5, 2026

PREPARED BY:
Sean Nathan, Interim Public Works Director


recommendation
RECOMMENDED ACTION:
Adopt a Resolution awarding a contract for the Carnegie Forum Boiler Replacement to Mesa Energy Systems, Inc., of West Sacramento ($94,363), authorizing the City Manager to execute Change Orders in an amount not to exceed $15,000 and appropriating funds from the Facilities Office Remodel Project in the amount of $10,000 and Fire Station 4 Stucco Project in the amount of $36,183 for a total new appropriation amount of $46,183.
body

BACKGROUND INFORMATION:
In recent years, various components of the boiler (heating) system at Carnegie Forum have required increasingly frequent maintenance and replacement. The system was installed in 1988 and has exceeded its expected useful life. Due to its age, and the difficulty in locating replacement parts, staff recommends the purchase and installation of a new boiler. The new boiler will be more reliable and reduce costs through its more efficient design.

This project includes removing and disposing of the existing boiler and auxiliary components, installing a new, high-efficiency natural gas-fueled boiler and expansion tank, and performing various plumbing, mechanical and electrical modifications to accommodate the installations.

The City bid the project utilizing the informal bidding procedures, a tabulation of the bids received and the Engineer's estimate is below:

Above/(Below)
Bidder Location Base Bid Engineers Estimate

Engineer's Estimate $60,000
*Champion Industrial Contracto...

Click here for full text