AGENDA TITLE:
title
Accept Improvements Under Contract for Traffic Signal and Lighting Project - Victor Road (SR 12) and Guild Avenue (PW)
end
MEETING DATE:
December 3, 2025
PREPARED BY:
Interim Public Works Director
recommendation
RECOMMENDED ACTION:
Accept improvements under contract for Traffic Signal and Lighting Project - Victor Road (SR12) and Guild Avenue.
body
BACKGROUND INFORMATION:
Steady growth in the industrial area east of SR 99 has resulted in additional traffic impacts at the intersection at Victor Road (SR 12) and Guild Avenue. This intersection was previously a 4-way intersection with stop controls on Guild Avenue. After receiving several requests for a traffic signal installation at this location, staff conducted a traffic signal evaluation that determined this intersection met the State criteria. Due to this being a State Route, the process of getting the signal designed, permitted, and constructed took the Traffic and Construction Management divisions of Public Works approximately eight (8) years.
This project installed curb ramps, crosswalk, traffic signal and lighting improvements at the Guild Avenue and Victor Road (SR 12) intersection. This project also relocated the raised median on Guild Avenue north of Victor Road to accommodate large truck turning movements as required by Caltrans.
On August 7, 2024, Council approved the plans and specifications and authorized advertisements for bids.
On November 6, 2024, Council awarded this project to St. Francis Electric in the amount of $903,999.00, and authorized the City Manager to execute change orders in an amount not-to-exceed $100,000.
On October 22, 2025, all work was completed in substantial conformance with the plans and specifications approved by City Council. The final contract price was $968,388.12 with five (5) change orders that totaled $64,389.12. Photos of the completed work are shown in Exhibit A, and a breakdown of the change orders are as follow...