Legislation Details

File #: 24-264    Name: Sidewalk Contract Amendment
Type: Resolution Status: Agenda Ready
File created: 5/20/2024 In control: City Council
On agenda: 6/5/2024 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution Authorizing City Manager to Execute Amendment No. 2 to 2021-2023 Sidewalk and Miscellaneous Concrete Repair Program to A.M. Stephens Concrete, Inc. of Lodi, CA, and Authorizing City Manager to Execute Additional Change Orders ($150,000) (PW)
Attachments: 1. Attachment 1 - Amendment No. 2, 2. Attachment 2 - Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA TITLE:
title
Adopt a Resolution Authorizing City Manager to Execute Amendment No. 2 to 2021-2023 Sidewalk and Miscellaneous Concrete Repair Program to A.M. Stephens Concrete, Inc. of Lodi, CA, and Authorizing City Manager to Execute Additional Change Orders ($150,000) (PW)
end

MEETING DATE:
June 5, 2024

PREPARED BY:
Public Works Director


recommendation
RECOMMENDED ACTION:
Adopt a Resolution Authorizing City Manager to Execute Amendment No. 2 to 2021-2023 Sidewalk and Miscellaneous Concrete Repair Program to A.M. Stephens Concrete, Inc. of Lodi, CA, and Authorizing City Manager to Execute Additional Change Orders ($150,000).

body
BACKGROUND INFORMATION:
This project consists of the construction, removal, and/or the replacement of curb, gutter, sidewalk, ramps, or other miscellaneous concrete items at various locations throughout the City on an as-needed basis.

On April 21, 2021, Council approved specifications and adopted a resolution authorizing the City Manager to award a contract to the lowest responsive bidder, not-to-exceed $250,000. On July 7, 2021, the City Manager executed the contract with Popuch Concrete Contracting, Inc., of Lodi, in the amount of $190,480. A.M. Stephens Concrete, Inc. purchased Popuch Concrete Contracting, Inc. in June, 2022 and a Consent to Assignment was executed to continue the contract under A.M. Stephens Concrete, Inc. on November 29, 2022. The contract was extended once with a unit costs adjustment based on the annual Consumer Price Index (CPI). Various change orders have been executed, increasing the total contract amount to $793,212 over the past four fiscal years. All change orders were either directly executed by Council action or by the City Manager as authorized by City Council. Many times, the change orders were to address the needs of other City departments for miscellaneous concrete work.

The current contract with A.M. Stephens Concrete, Inc. is set to expire on June 30, 2024. The contract...