AGENDA TITLE:
title
Adopt a Resolution Awarding Contract for Hutchins Street Resurfacing Project to Knife River Construction of Stockton ($1,370,475); Authorize City Manager to Execute Change Orders ($150,000); and Appropriate Funds ($1,520,476) (PW)
end
MEETING DATE:
May 7, 2025
PREPARED BY:
Public Works Director
recommendation
RECOMMENDED ACTION:
Adopt a Resolution Awarding Contract for Hutchins Street Resurfacing Project to Knife River Construction of Stockton in the amount of $1,370,475, Authorize the City Manager to Execute Change Orders in an amount not-to-exceed $150,000, and appropriate funds in the amount of $1,520,476.
body
BACKGROUND INFORMATION:
This project includes localized pavement repair and the application of approximately 31,000 square yards of rubberized asphalt cape seal and fiberized slurry seal. The project limits will include Hutchins Street (from Lodi Ave to Kettleman Lane) as shown on Exhibit A.
The rubberized asphalt cape seal is a combination of a rubberized chip seal comprising the bottom layer followed with an upper layer of fiberized slurry seal (slurry seal with strands of glass fiber added). The rubberized cape seal with fiberized slurry will be applied within the project limits.
While the asphalt overlay is superior in ride quality, these pavement rehabilitation alternatives are expected to extend the life of deteriorated roads by around one-half of that of an overlay, at approximately one-third of the cost.
This project will be funded by the Federal Transportation Improvement Program, which only applies to arterials and high volume streets. Hutchins Street was selected for resurfacing based on several considerations including the citywide pavement index survey, Hutchins Street being a North-South arterial and a gateway into the City, its high traffic volume, and poor pavement conditions.
Specifications for this project were originally approved on January 15, 2025. On March 26, 2025, the City received th...
Click here for full text